Yeah. I I think All right, it is 6 o'clock. Um, good afternoon everyone or evening. It's kind of a in between time right now. Um, we're here to discuss the McCart McFersonson roadway construction project. Thank you all for joining. Um,

2
00:00:49.200 --> 00:01:06.880
I'm Abby Tucker. I'm the city of Fort Worth project manager and um as you can see I've got the some of our team listed on the screen as well. Um so let's go ahead and get started. I'll go to the next slide. Um just wanted to give a special shout out to Council District 6 and all the

3
00:01:06.880 --> 00:01:26.960
work they do for the city. Um I'm not sure if Council Member Hall or any of their staff are here, but if so, um feel free to introduce yourselves. Say hi to everyone. I'll take that as no, but if anyone jumps on and we'll we can let them talk

4
00:01:26.960 --> 00:01:42.479
whenever. So, all right. So, for the agenda for this evening, um we're going to go over the current conditions of the um roadway or lack thereof um at the product site. We're going to go through the product objective, the improvements,

5
00:01:42.479 --> 00:01:58.719
cost, schedule, and then last the funding. So, currently what's out there today, um, there's a two-lane roadway on McCart from Valley Bin Drive to Cayman Drive. And then I'm sorry, I don't know that

6
00:01:58.719 --> 00:02:13.760
that's right. Yeah, I think that's right. Um, and then, sorry, and then there's a two-lane roadway on McFersonson, and that's from West Cleburn to east of Mlan Farm Drive. Um, the rest of this project will be new construction. Um, it's pretty much

7
00:02:13.760 --> 00:02:30.080
undeveloped land there. Um yeah, so we'll get into um what it looks like today. As you can see um we've got McCart um towards the north side and then Rising Road McFerson and we'll be expanding McCart and McFerson.

8
00:02:30.080 --> 00:02:45.519
So the main project objectives for this project are to increase safety and improve connectivity by adding this corridor um for the city. And then here is an overview of the proposed improvements for this project.

9
00:02:45.519 --> 00:03:00.480
Um, as you can see, we've got um expanding McCart from Rising Road all the way down to Twin Leaf on the south and expanding McCart McFerson or sorry, McFerson Drive, McFerson, whatever to um

10
00:03:00.480 --> 00:03:16.800
from West Clevern to McCart. Um and then here are a couple snapshots from the plans of the typical sections for this project. Um mostly McCart will be from the north side of the project down to

11
00:03:16.800 --> 00:03:32.959
McFerson will be a two-lane divided roadway with median um cutouts for left turns. And then from McFersonson all the way down to Twin Leaf, it will be a two-lane roadway with um continuous two-way left turn lanes.

12
00:03:32.959 --> 00:03:48.560
And then on McFersonson, um it'll be a divided roadway just like McCart um on the north side of the project. Um two lanes on each side with a left turn lane um going on to uh Cleburn.

13
00:03:48.560 --> 00:04:05.920
So here is a bit of a zoomed in version for the proposed improvements um on McCart. And this is the segment from Risinger all the way to North Crowley Clevern. As you can see, we're going to be doing, like I said, a four-lane divided highway or roadway um with

14
00:04:05.920 --> 00:04:21.840
median cutouts, and those will be at Aruba Lane and Cayman Drive. Um and then on the south side of this image, obviously, we're going to have a roundabout um connecting the cart to North Crowley Clever Road. And then here's a zoomed in version just

15
00:04:21.840 --> 00:04:39.040
of those um median cutouts. Like I said, they're going to be for Cayman Drive and Aruba Lane. And then here's a zoom in of the um roundabout at North Carly Cleburn. Um as for the proposed improvements for the rest of the project, we're going to

16
00:04:39.040 --> 00:04:56.400
get into some of the other segments. Um as an overview of this part, um we have another roundabout being proposed and three bridges o um over bodies of water. Um yeah, so this first section is North Carley Cleburn. Well, McCart from North

17
00:04:56.400 --> 00:05:10.960
Carolina Carly Clevern to McFersonson Boulevard. Um, as you can see, like I said for the previous segment, um, this is going to be a four-lane divided and it'll go in directly to the roundabout. The next segment we'll talk about is

18
00:05:10.960 --> 00:05:27.680
McFersonson Boulevard from um, Crowley Cleburn, I think, to McCart. Um, and it'll be a four-lane divided as well. You can see the bridge highlighted in orange right there on the screen. And that'll be going over um a body of water.

19
00:05:27.680 --> 00:05:42.960
And then going to the south limits of the project from McFerson all the way to Twin Leaf. It'll be mostly a um a two-way two um lane roadway with uh um two

20
00:05:42.960 --> 00:06:00.880
two-way left turn lanes. And then um obviously in the north side is that same route that we saw in the previous slide for McFersonson. All right. Um getting into the project cost and schedule. Um we're going to be constructing this project for $35.4

21
00:06:00.880 --> 00:06:16.080
million. Um the total project budget um for the city for this project is 48.8 million. And then as for the project schedule, um construction is going to be starting next month in July of 2026 and will complete substantially um in July

22
00:06:16.080 --> 00:06:31.919
of 2028, giving this contract a two-year time span. Um as far as project funding sources goes, um most of this project is funded by the bond program and transportation impact fees and there are some various

23
00:06:31.919 --> 00:06:48.000
other um funding sources as well. And then just a little plug for our My Fort Worth app. Um you can de download this to your devices from the app store and Google Play. Um you can report issues um request service

24
00:06:48.000 --> 00:07:04.319
um you know anything like that that you want to get in contact with someone from the city. You can uh use this app. It's very helpful and um it'll get get your concerns in contact with the correct people. And then this is my last slide and we'll take questions right after. This is my

25
00:07:04.319 --> 00:07:22.199
contact information. Um the contact information for the construction project manager with Sakola and then the city of Fort Worth inspector. Um and now um if you'd like to place any comments in the chat um we'd be happy to answer your questions or get back to you if we can't answer them immediately.

26
00:07:24.750 --> 00:07:41.759
[snorts] >> Hey there. Good afternoon. Can you hear me? Okay. >> Yes. >> Hi. This is Maria and Joseph. Um, we are residents of the territories community which is in the the section between West Clebburn Road and what would be the

27
00:07:41.759 --> 00:07:56.800
roundabout extension to McCart. >> Is that going to be um like a is that going to start here in the next month or is there going to be phasing for these this entire project? >> Um, yeah, there will be phasing. I'm

28
00:07:56.800 --> 00:08:13.199
I'll let um Mario Cakola folks talk more about that. I'm not really sure what'll start when. Um, and I'm not sure what details we can give at this moment, but but yeah, it'll be mobilized. The the entire contract will be mobilized in July. I don't know

29
00:08:13.199 --> 00:08:28.319
if anyone wants us. >> Yeah. Are the are the folks from Marisola, can they unmute themselves and maybe speak as to generally what the first phase of the project is going to be from where to where and maybe second phase, maybe third phase?

30
00:08:28.319 --> 00:08:44.320
Uh not at this time, but we're uh developing the schedule. Um yeah, I guess to answer the lady's question, there will be uh some phased intersection work at uh Cleveland and

31
00:08:44.320 --> 00:09:03.200
Cleburn and McCart um mix tie-in and around the police building. >> Cool. And um [clears throat] following up on that same uh question, and this is uh Joseph uh speaking with Maria. Um do do y'all know if there's

32
00:09:03.200 --> 00:09:22.240
any sort of I guess in terms of that phasing if y'all are planning on doing any sort of closure in terms of the open section of McFerson? Um I believe um >> we have to develop our traffic control

33
00:09:22.240 --> 00:09:39.120
plan submitted to the city for approval. So we'll be working on that um and like I said before right now it should be a phased tiein um to allow traffic through.

34
00:09:39.120 --> 00:09:54.959
So, what we can do is those questions that are we're unable to answer at this point, we'll we'll take note of them and we will post uh the answers on the project web page and we can I can find the project web page here real quick and

35
00:09:54.959 --> 00:10:11.839
put the the link in the chat so you guys know where that web page is and we'll do updates of that web page every month so you can have u more up-to-date information. >> That that would be great. And really the these questions stem from um there's two

36
00:10:11.839 --> 00:10:26.959
entrances to our community. One is on West Cleon Road and one is on McFersonson right now. Um but I'm I'm anticipating that that McFersonson entrance is probably going to be blocked for some time. So just trying to understand what our options are going to be when that happens because West

37
00:10:26.959 --> 00:10:51.760
Cleburn Road does get backed up quite a bit um especially during school season. So just that that's where those questions were coming from. Understood. Thank you so much. >> Yes. Hello, my name is Jerry. I got a

38
00:10:51.760 --> 00:11:09.360
question on the extension park going from McFersonson down to Twin Leaf. Was there a consideration to make that fourlane vice two-lane because of the massive amount of uh influx of homes being built out there? seems like a two lane is just not enough,

39
00:11:09.360 --> 00:11:27.160
>> right? So, so the master thoroughare plan takes into account um anticipated volumes for the ultimate buildout of that section and it didn't warrant four lanes. So, it's going to be a two-lane section with a two-way left turn lane.

40
00:11:30.880 --> 00:11:45.600
Is there any anticipation how long after the completion of this that they would turn into a fourlane? >> At at this time it's not anticipated to be a four a fourlane um at all. The MA we have a what we call

41
00:11:45.600 --> 00:12:01.920
a mass thorfare plan which maps all the city streets that are in the ground now and that are needed in the future uh based on anticipated traffic volumes from the various areas once they fully developed

42
00:12:01.920 --> 00:12:18.000
takes into account uh land use. So if you have a green uh green field or pasture that's going to be say a single family subdivision that is taken into account the density of the homes that are going to be built there if it's a thousand homes what have you and that is

43
00:12:18.000 --> 00:12:36.079
taken into account to predict what the uh number of lanes are going to be needed on every road. So based on the masterfair plan only two lanes are needed. >> Yeah. I believe that's sort of towards the the limits of Fort Worth and um

44
00:12:36.079 --> 00:13:04.959
the road doesn't extend much further south other than those one or two subdivisions that are that are there. >> Okay. Thank you. >> Sure. You're welcome. Abby, there are a couple of questions in the chat, so I didn't know if you wanted

45
00:13:04.959 --> 00:13:21.279
me to just go ahead and read those to you because I know you were saying that you can't see them while you're sharing your screen. >> Yeah, I I fig I forgot they were there, but yeah, I see them now. Um, okay. Yeah, we can go down the list. Thank you. Um, the first question is asking

46
00:13:21.279 --> 00:13:35.600
about a section of road near Crowley High School that is called McCart. Will this extension connect to that roadway? Um, I believe you're asking about I'm not sure what the question means. If anyone else wants to jump in,

47
00:13:35.600 --> 00:13:56.480
>> see, I can get um new Crowley High School that is C. Yeah, I'm not familiar with Crowley High School or >> the M Mart where you you're going to Twin Leaf. Um that is called Mart. I

48
00:13:56.480 --> 00:14:12.079
believe that's what he's referring to is where McCart will connect down at Twin Leaf and it goes from there down to the about the city limits of Crowley and there then it's called Eagle and it gets down to Crowley High School. But I assume that he's asking about that >> portion that stops at Twin Leaf

49
00:14:12.079 --> 00:14:30.240
currently. Yeah, the project will stop at Twin Lift >> and further much further south. I'm not sure if that's still within the city of city of Fort Worth limits or whether that's Crowley. >> It goes a little bit further in the the portion that's still in Fort Worth City

50
00:14:30.240 --> 00:14:48.320
is is called McCart. And as soon as it turns into Crowley, the road is then called Eagle. But so it looks like you're connecting to the existing Mart. >> That's correct. >> Is that the limit? Yes. >> Okay. That he's talking about the

51
00:14:48.320 --> 00:15:04.480
stretch further south, >> well further south than our project limits Ro. >> Oh, >> I think I see the high school. The high school is sort of uh north of Mirror Verde Drive. >> Yes.

52
00:15:04.480 --> 00:15:21.839
>> Yes, that is. I'm sorry. That's the elementary school. Where's the high school? The high school is near Eagle Drive and it's about maybe six or eight blocks south of where you're connecting it Twin Leaf and Mart. So yes, it does connect

53
00:15:21.839 --> 00:15:40.240
to that same Mart >> on the north end. >> Does that make sense? North of >> of the high school. I'm trying to find Eagle Drive, Patricia, but um the roads are on

54
00:15:40.240 --> 00:15:56.639
>> the cart changes its name to Eagle Drive right next to Crowley High School when it goes into the town of Crowley. >> Yeah, I can't see it on the map, but I assume there is a big field football field, so that must be the high school.

55
00:15:56.639 --> 00:16:11.199
Um yeah, so that's that's not planned to be improved at this time. No, but it will connect to it which is what the question said is >> but it it is connected today. It is actually connected today. There is a

56
00:16:11.199 --> 00:16:26.399
road there, but yeah, it won't be I think that goes beyond the city limits because I'm not showing uh the master thorough plan extended into that section. And I wish I had my

57
00:16:26.399 --> 00:16:48.800
see if I can look up the city limits. >> Okay. Um we can >> Sean, do you feel like we've answered your question or are you Do you have further questions? You can either ask or write it in the chat. >> Oops.

58
00:16:48.800 --> 00:17:23.439
>> So that I can multitask and use both all of my um monitors. I need to close my laptop so that I can have three monitors and I can look around better. >> I apologize. >> No problem. Okay, it looks like um we were able to

59
00:17:23.439 --> 00:17:39.280
help John's question. >> Okay, >> great. Thank you. Um the next question is from Greg um asking about the roundabout at North Crowley Cleburn and how long that phase will take. Um we like they said we don't have a specific

60
00:17:39.280 --> 00:17:55.679
schedule yet but it it's not going to take two years to just do the roundabout. So it'll be phase construction. Um like they said earlier um but if you have any specific questions as the project goes on you know you um I have my contact

61
00:17:55.679 --> 00:18:10.880
information listed and you can reach out >> work. So I just have the answer to um the question that is that segment u right across the street from the high school is in fact within Crowley. It's not within Fort Worth or so we wouldn't be

62
00:18:10.880 --> 00:18:31.280
able to extend the road there. That's why the mass thorough fair plan doesn't go that far south. >> That's my way to work on toll road. >> Oh I'm sorry. What was that?

63
00:18:31.600 --> 00:18:52.640
That's my way to work. Chisum Toll Road. >> You're coming from the east going west to Chisum. Is that what you're saying? >> Yes, ma'am. >> Okay. >> Yeah. Yeah. The sale limit is um just a little

64
00:18:52.640 --> 00:19:09.520
further south from where the project ends. I just uh pasted the link to the project web page in uh on the chat. So if you guys if you all want to top it or link on it and you

65
00:19:09.520 --> 00:19:25.120
know keep it on your on your desktops uh as a u as a shortcut that that's project web page and we'll we update that web page every month and we can post uh some of the answers to the questions uh here within the next uh few weeks and we'll

66
00:19:25.120 --> 00:19:40.480
post updates on the project maybe facing uh those kinds of information and obviously Aby's name is on that project web page as is on this slide. So, if you want to take a shot of this slide so you have her name and contact information as

67
00:19:40.480 --> 00:19:57.520
well as the inspector. >> So, any questions that you have, I would I would ask you to please address them to Abby and or the inspector. Um, and we'll forward any questions to the contractor. >> Yes. >> Get you some answers.

68
00:19:57.520 --> 00:20:15.039
>> And it looks like the next question that I see in the chat is, will there be traffic lights anywhere on this proposal? Um, the answer is no. Um, [clears throat] there is I think there's a traffic light currently on McPerson. Correct me if I'm wrong. Um, but we're not adding any,

69
00:20:15.039 --> 00:20:47.039
so there will only be roundabouts added um, with this project. >> No traffic light on Clear. >> Oh, I'm sorry. Okay. All right. Um, I don't know if anyone else has any questions. >> I I might have been late, but uh can you

70
00:20:47.039 --> 00:21:04.159
publish that uh link to the to the project page where we can get updates from time to time? >> Uh, yes. It's um I don't know if you can look in the chat right now. >> Um, >> put it in the chat. I'll copy it again. It's the very last one. I just recopied

71
00:21:04.159 --> 00:21:21.600
it on chat. >> Thank you. >> Yes. And the webinar recording will be I think it's posted to our um website as well. Um >> that's correct. >> So that'll also be posted. That was a question in the chat. >> The presentation and even a link to the

72
00:21:21.600 --> 00:21:38.880
meeting uh recording. >> Yes. And then is there a map of the proposed roundabouts? Um, we do have plan sheets. >> Um, what is being constructed, but I don't know what we can and cannot share. That might be a

73
00:21:38.880 --> 00:21:54.559
question for Raul. Um yeah, we can't we can't share the construction um plans with you all, but we can we can certainly put a um a rendering of what the roundabout is going to look like and maybe you know

74
00:21:54.559 --> 00:22:24.480
the approaches from all four sides. Yeah, and like Raul said, we'll be updating the project web page um throughout the duration of this project. And um feel free to check in on it from time to time. And if you don't, you know, see what you want on there, just

75
00:22:24.480 --> 00:22:45.760
reach out and we'll be happy to answer any questions that we can. Yes, John. Uh yeah, this the project does connect to Twin Leaf. That's that's one of the goals of the project is to connect uh uh Crowley Cleveland all the way to Twin Leaf, which is sort of a

76
00:22:45.760 --> 00:23:17.760
dead end on the south end. So Twin Leaf will be able to turn left and go north, go all the way to uh Crowley, Cleburn or Rising Road or anywhere north of there. All right. I don't know if we have any

77
00:23:17.760 --> 00:23:35.120
more questions or if we didn't answer one in the chat that I skipped over, just let me know and we can answer anything. Will there be coordination with police on the segment by the police station? That's a question we just got.

78
00:23:35.120 --> 00:23:52.480
>> Yeah, the police station is at the very uh intersection right at the intersection with Risinger. Um we don't anticipate that being u in the way the project the project starts a little further south of the police station

79
00:23:52.480 --> 00:24:10.559
>> but c certainly we will coordinate with them if we we're impacting the >> yes >> the yeah the police station. >> All right. Uh the new the next question is about the old Cleber and Crowley Junction Road. um we um that's not part of this

80
00:24:10.559 --> 00:24:27.039
project, but um um feel free to reach out to the city and we can get you in contact with the project manager for for that project. I I believe I just looked it up recently and there is a project at that location. Um

81
00:24:27.039 --> 00:24:46.640
and you might even be able to find it on that same web page that Raul shared our project with if you um use the search function >> St. Vincent Road >> flyer in the mail shows a generic map of the project, folks.

82
00:24:46.640 --> 00:25:02.720
>> Yeah, the the flyer was just a generic map um of the limits of the project. And then St. Vincent Road, is it going to have direct access to McCart? I don't know if someone can pull that up on Google Maps. I don't currently have it open.

83
00:25:02.720 --> 00:25:30.080
See if I can pull that up. >> Okay. Louise St. Vincent Road St. Vincent Road sounds like uh Rainbow Ridge, doesn't it? >> Yeah.

84
00:25:30.080 --> 00:25:52.720
>> Correct. So Abby, can you go to north of the first roundabout? The north roundabout. >> Yeah, >> I think it does connect. >> It's the next road just south of >> just south of Cayman Drive.

85
00:25:52.720 --> 00:26:15.039
Oh, >> it's it's yeah, it's it's got to connect. It may not be shown here and if it's not in the plans, we will connect it because that's that's the goal of there's no reason why we wouldn't connect it on the northbound lanes.

86
00:26:15.039 --> 00:26:57.440
So, we we'll take a look at that, but it's it certainly will connect Sweet. [clears throat] Yeah, that subdivision Rainbow Ridge is all U Caribbean islands. That's why I knew that St. Vincent sounded like that area. It's Cayman Drive, St. Vincent,

87
00:26:57.440 --> 00:28:02.000
St. Kit, St. Lucia, St. parts. >> All the things. All the things. Correct. I'll go back to my contact information. >> Go USA. Yes. [laughter] I think if we don't have any more questions, we can adjourn. We appreciate

88
00:28:02.000 --> 00:28:18.080
everybody showing up and again, yeah, check out the web page. Uh we'll be updating that once a month with you. >> We did have one question pop up. >> Yes. >> Yes, I see. >> When will the project begin? >> The Yeah. Um like Greg said in the chat,

89
00:28:18.080 --> 00:28:51.520
July of 2026, next month. Greg, we're going to make an honorary part of the team, the project team. >> You're doing really good. >> All right, looks like we're good. Um, thank you all for joining. Uh we really appreciate y'all's time taking you know

90
00:28:51.520 --> 00:29:07.760
an evening out to discuss this project. So we really appreciate it. >> Thank you all very much. Have a good evening. >> And Abby, can I get your attention one second while when everybody's gone? >> Yeah, sure. >> Yes. Yeah, no problem. >> Yeah.

91
00:29:07.760 --> 00:29:30.000
>> Thank you. >> Thank you. >> Thank you. Have a good evening. Just a little a little nugget. I know the names of those. I'm familiar with the names of those trees because I was the project manager. That's how long I've been with the city when that subdivision got built. On the very first

92
00:29:30.000 --> 00:29:56.960
phase of that built, I was the project manager. So, I remember >> uh the names of the streets they they ring familiar. >> You got a good memory. I swear >> even after 23 years [laughter] >> ma aside I I sent you a request for more

93
00:29:56.960 --> 00:30:14.640
cat files. Don't know if you've seen it. >> Yes, and I'm gathering that information. You should have the link to be able to access and download that information here within the next 30 minutes or so. >> Is that how we transmitted them last time with a link?

94
00:30:14.640 --> 00:30:29.520
>> Yes. >> I wasn't able to upload to the eBuilder last time. So, I just sent y'all a link to be able to access and download. >> Okay. >> If you don't copy the faults that I copied, that way they have the link and they can download it themselves. >> Yes, sir.

95
00:30:29.520 --> 00:30:55.440
>> Yep. Did you want me to set up a quick team's call Raul? >> Yeah, that's what I was here. Quick teams call. It's just go to go over a few things that I want to make sure that we're all on the same page. >> Okay, >> let's go ahead and u

96
00:30:55.440 --> 00:31:10.799
>> Yeah, let's go ahead and quick up. You know what? I should be a we should be able to call Mansa on teams even when he's not >> part of the city. I've done that with external >> Oh yeah, that's true. >> Yes, you should. >> Yeah, there you are. So,

97
00:31:10.799 --> 00:31:26.880
>> you you'll answer. Let me see. Uh chat. No. Yeah, let me see. >> Let me know if you >> if it's ringing on your end. >> Yep, it's ringing. >> Okay, so we can hop off the WebEx and then Abby, I'll call you. >> Sounds good. >> Okay, thank you all. Thank you very much.

98
00:31:26.880 --> 00:31:30.039
>> Thank you.